Since the start of 2022, under the supervision of Cédric Fyen Gagnon, Charles-David Laurin, Dann Bouffard, Jean-François Pellerin and myself, the REM Laval project - Grand-Moulin, Sainte-Dorothée and Ile-Bigras stations - has been well underway. Some twenty electricians are hard at work on the complete installation of electrical services and distribution for our customer's three (3) stations. Currently, grounding, sub-slab and surface conduits are being completed on all three (3) sites, and crews are progressively starting cable pulling, telecom rooms and electrical equipment installation. This work should keep us busy until summer 2023. Best wishes to the whole team!

 

 

 

 

 

 

 

 