2021-07-21
Work on the site is well underway.
The two main electrical rooms are in the final stages in preparation of the commissioning which is planned after the construction vacation. Our teams have installed the 25KV cables to these two rooms from the Côte-Vertu station. This station is currently closed in order to proceed with the installation of a track switch to the new garage.
DAWCO completed the scope of work on schedule allowing the STM to return the station back in service by the end of August 2021.
We are continuing our work in the main building (SA Atelier) to allow the STM to begin testing in the fall.
I want to thank my team for their hard work and determination to get this project done on time.